NPRR717

Summary

Title: Clarification of EPS Metering Exception for ERS Generation
Next Group:
Next Step:
Status: Approved on 10/13/2015
Effective Dates:
11/01/2015

Action

Date Gov Body Action Taken Next Steps
10/13/2015 BOARD Approved
09/24/2015 TAC Recommended for Approval Board for consideration
09/10/2015 PRS Recommended for Approval TAC for consideration
08/13/2015 PRS Recommended for Approval PRS for Impact Analysis review

Voting Record

Date Gov Body Motion Result
10/13/2015 BOARD To approve NPRR717 as recommended by TAC in the 9/24/15 TAC Report Passed
09/24/2015 TAC To recommend approval of NPRR717 as recommended by PRS in the 9/10/15 PRS Report Passed
09/10/2015 PRS To endorse and forward to TAC the 8/13/15 PRS Report and Impact Analysis for NPRR717 Passed
08/13/2015 PRS To recommend approval of NPRR717 as submitted Passed

Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

Background

Status: Approved
Date Posted: Jul 10, 2015
Sponsor: Austin Energy
Urgent: No
Sections: 10.2.3
Description: This Nodal Protocol Revision Request (NPRR) adds language in Section 10.2.3 to exempt generation offering Emergency Response Service (ERS) during the current contract period from the ERCOT-Polled Settlement (EPS) metering requirement and allow the EPS-exempt ERS Generator to export energy to the ERCOT System during equipment testing.
Reason: Meets Strategic goals, Market efficiencies or enhancements, reduces ambiguity