NPRR694

Summary

Title: Non-Spin Schedule Requirements
Next Group:
Next Step:
Status: Approved on 08/11/2015
Effective Dates:
09/01/2015

Action

Date Gov Body Action Taken Next Steps
08/11/2015 BOARD Approved
07/30/2015 TAC Recommended for Approval Revision Request Consideration
06/11/2015 PRS Recommended for Approval TAC for consideration.
05/14/2015 PRS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
08/11/2015 BOARD To approved NPRR694 as recommended by TAC in the 7/30/15 TAC Report. Passed
07/30/2015 TAC To recommend approval of NPRR694 as recommended by PRS in the 6/11/15 PRS Report. Passed
06/11/2015 PRS To endorse and forward to TAC the 5/14/15 PRS Report and Impact Analysis for NPRR694. Passed
05/14/2015 PRS To recommend approval of NPRR694 as submitted. Passed

Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

Background

Status: Approved
Date Posted: Apr 9, 2015
Sponsor: GDF Suez Energy Marketing
Urgent: No
Sections: 6.5.5.2
Description: This Nodal Protocol Revision Request (NPRR) defines the Real- Time Inter-Control Center Communications Protocol (ICCP) scheduling requirements for Off-Line Non-Spin, On-Line Non-Spin, and On-Line Non-Spin using Off-Line power augmentation technology.
Reason: Addresses current operational issues