MIS LOG IN

NPRR539

Summary

Title Amend Wholesale Storage Load Definition
Next Group
Next Step
Status Approved on 09/17/2013
Effective Dates
10/01/2013

Action

Date Gov Body Action Taken Next steps
09/17/2013 BOARD Approved
07/02/2013 TAC Recommended for Approval ERCOT Board consideration.
06/20/2013 PRS Recommended for Approval TAC Consideration
05/16/2013 PRS Recommended for Approval PRS for Impact Analysis review.

Voting Record

Date Gov Body Motion Result
09/17/2013 BOARD To approve NPRR539 as recommended by TAC in the 7/2/13 TAC Report. Passed
07/02/2013 TAC To recommend approval of NPRR539 as recommended by PRS in the 6/20/13 PRS Report. Passed
06/20/2013 PRS To endorse and forward the 5/16/13 PRS and Impact Analysis for NPRR539 to TAC Passed
05/16/2013 PRS To recommend approval of NPRR539 as submitted. Passed

Background

Status: Approved
Date Posted: Apr 26, 2013
Sponsor: Mark Bruce on behalf of Emerging Technologies Working Group (ETWG)
Urgent: No
Sections: 2.1
Description: This Nodal Protocol Revision Request (NPRR) adds thermal energy storage associated with turbine inlet chilling to the list of technologies eligible for Wholesale Storage Load (WSL) Settlement treatment. At its April 12, 2013 meeting, WMS endorsed this NPRR and directed Emerging Technologies Working Group (ETWG) to file it. There was one abstention to the WMS motion from the Consumer Market Segment.
Reason: The WSL definition identifies specific energy storage technologies eligible to receive WSL Settlement treatment and in order for thermal energy storage associated with turbine inlet chilling to receive WSL settlement treatment, it must be added to the list.

Key Documents

Related Content