MIS LOG IN

NPRR269

Summary

Title: Synchronization of PRR830, Reactive Power Capability Requirement
Next Group:
Next Step:
Status: Approved on 11/16/2010
Effective Dates:
12/01/2010

Action

Date Gov Body Action Taken Next Steps
11/16/2010 BOARD Approved
11/04/2010 TAC Recommended for Approval ERCOT Board for consideration.
11/18/2010 PRS Recommended for Approval TAC for consideration.
09/23/2010 PRS Recommended for Approval PRS for Impact Analysis review.

Voting Record

Date Gov Body Motion Result
11/16/2010 BOARD To approve NPRR269 as recommended by TAC in the 11/4/10 TAC Report. Passed
11/04/2010 TAC To recommend approval of NPRR269 as amended by the 11/1/10 ERCOT comments and as revised by TAC. Passed
11/18/2010 PRS To endorse and forward the 9/23/10 PRS Report as revised by PRS and the Impact Analysis for NPRR269 to TAC. Passed
09/23/2010 PRS To recommend approval of NPRR269 as amended by the 9/20/10 Luminant comments. Passed

Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

Background

Status: Approved
Date Posted: Sep 9, 2010
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 2.2, 3.10.7.3, 3.15, 3.15.1, 3.15.2, 6.5.7.7, 10.3.2.2, 10.3.2.3, 11.1.5
Description: This Nodal Protocol Revision Request (NPRR) synchronizes the Nodal Protocols with Protocol Revision Request (PRR) 830, Reactive Power Capability Requirement, approved by the ERCOT Board on 11/17/2009. In addition, Nodal Protocol references to Point of Interconnection (POI) are being updated to reflect the defined term where appropriate.
Reason: To synchronize the Nodal Protocols with PRR830.

Key Documents