NPRR1324

Summary

Title Clarification of the Process to Determine RUC Warmth State
Next Group
Next Step
Status Approved on 07/09/2026
Effective Dates
08/01/2026

Action

Date Gov Body Action Taken Next Steps
07/09/2026 PUCT Approved
06/01/2026 BOARD Recommended for Approval Revision Request Consideration
04/29/2026 TAC Recommended for Approval Revision Request Consideration
04/15/2026 PRS Recommended for Approval Revision Request Consideration
03/11/2026 PRS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
07/09/2026 PUCT to approve NPRR1324 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization Passed
06/01/2026 BOARD to recommend approval of NPRR1324 as recommended by TAC in the 4/29/26 TAC Report Passed
04/29/2026 TAC to recommend approval of NPRR1324 as recommended by PRS in the 4/15/26 PRS Report Passed
04/15/2026 PRS to endorse and forward to TAC the 3/11/26 PRS Report and 2/24/26 Impact Analysis for NPRR1324 Passed
03/11/2026 PRS to recommend approval of NPRR1324 as submitted Passed

Background

Status: Approved
Date Posted: Feb 24, 2026
Sponsor: ERCOT
Urgent: No
Sections: 5.6.2
Description: This Nodal Protocol Revision Request (NPRR) clarifies the process currently used by ERCOT to determine the startup warmth state (i.e., hot, intermediate, or cold) of a block of contiguous Reliability Unit Commitment (RUC)-Committed Hours. Since December 2010, ERCOT has determined the startup warmth state of a block of contiguous RUC-Committed Hours by counting the time between the start of the first RUC hour in a block of startup-eligible RUC-Committed Hours to the most recent time the Resource went Off-Line prior to the first RUC-Committed Hour of the block. This NPRR is submitted for transparency to codify that practice into the Protocols.
Reason: General system and/or process improvement(s)