NPRR1147

Summary

Title Update and Improve Notification and Evaluation Processes Associated with Reliability Must-Run (RMR)
Next Group BOARD
Next Step Board for consideration
Status Pending

Action

Date Gov Body Action Taken Next steps
01/24/2023 TAC Recommended for Approval Board for consideration
12/08/2022 PRS Recommended for Approval TAC for consideration
11/11/2022 PRS Recommended for Approval PRS for Impact Analysis consideration
09/15/2022 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
01/24/2023 TAC To recommend approval of NPRR1147 as recommended by PRS in the 12/8/22 PRS Report Passed
12/08/2022 PRS To endorse and forward to TAC the 11/11/22 PRS Report and 8/15/22 Impact Analysis for NPRR1147 Passed
11/11/2022 PRS To recommend approval of NPRR1147 as submitted Passed
09/15/2022 PRS To table NPRR1147 and refer the issue to ROS Passed

Background

Status: Pending
Date Posted: Aug 15, 2022
Sponsor: ERCOT
Urgent: No
Sections: 3.14.1.1, 3.14.1.2, 3.14.1.3, 3.14.1.5, 3.14.1.9, 3.14.1.10, and 22E
Description: This Nodal Protocol Revision Request (NPRR): adds a 20 MW capacity threshold for conducting a Reliability Must-Run (RMR) reliability analysis; requires that an RMR study be conducted when a Resource Entity gives notice that a Generation Resource is ceasing operation permanently due to a Forced Outage; and updates Section 22, Attachment E to require Resource Entity to provide information about deactivation of Transmission Facilities as part of the suspension of operations of the unit.
Reason: Market efficiencies or enhancements / Clarification and consistency