MIS LOG IN

NPRR1098

Summary

Title Direct Current Tie (DC Tie) Reactive Power Capability Requirements
Next Group
Next Step
Status Approved on 03/31/2022

Action

Date Gov Body Action Taken Next steps
03/31/2022 PUCT Approved
03/07/2022 BOARD Recommended for Approval Revision Request Consideration
01/31/2022 TAC Recommended for Approval Revision Request Consideration
12/14/2021 PRS Recommended for Approval Revision Request Consideration
11/10/2021 PRS Deferred/Tabled Impact Analysis Consideration
10/14/2021 PRS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
03/31/2022 PUCT to approve NPRR1098 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization Passed
03/07/2022 BOARD to recommend approval of NPRR1098 as recommended by TAC in the 1/31/22 TAC Report Passed
01/31/2022 TAC to recommend approval of NPRR1098 as recommended by PRS in the 12/14/21 PRS Report Passed
12/14/2021 PRS to endorse and forward to TAC the 11/10/21 PRS Report as amended by the 11/29/21 ERCOT comments and the Impact Analysis for NPRR1098 with a recommended priority of 2022 and rank of 2530 Passed
11/10/2021 PRS To table NPRR1098 Passed
10/14/2021 PRS to recommend approval of NPRR1098 as submitted Passed

Background

Status: Approved
Date Posted: Sep 29, 2021
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 3.15.1, 3.15.4 (new), and 6.5.6
Description: This Nodal Protocol Revision Request (NPRR) establishes Reactive Power capability requirements for new Direct Current Ties (DC Ties) interconnecting to the ERCOT System and existing DC Ties replaced after January 1, 2021.
Reason: Regulatory Requirements

Key Documents

Related Content