NPRR076

Summary

Title: Synchronization of Emergency Electric Curtailment Plan (EECP) Event Realignment
Next Group:
Next Step:
Status: Approved on 12/11/2007
Effective Dates:
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (01/01/08 Nodal Protocols Library)

Voting Record

Date Gov Body Motion Result
12/11/2007 BOARD Approve NPRR076 as recommended by TAC Passed
11/29/2007 TAC Recommend approval of NPRR076 and to instruct ERCOT to design the Nodal system in such a way to allow the RDF to be reduced to zero. Passed
11/15/2007 PRS To forward the Recommendation Report and IA to TAC. Passed
10/18/2007 PRS Recommend approval of NPRR076 as revised by DSWG comments. Passed
09/20/2007 PRS To table further consideration of NPRR076 until the October PRS meeting to allow for additional comments. Passed
08/23/2007 PRS
07/19/2007 PRS Remand NPRR076 to WMS and direct that the Demand Side Working Group (DSWG) further review the Load Resource selection process in Section 6.5.9.4.1, EECP Steps. Passed

Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

Background

Status: Approved
Date Posted: Jul 2, 2007
Sponsor: TPTF
Urgent: No
Sections: 2.1, 2.2, 6.5.7.5, 6.5.9.4, 6.5.9.4.1 (new), 6.5.9.4.1
Description: This Nodal Protocol Revision Request (NPRR) synchronizes the Nodal Protocols with PRR682, EECP Event Realignment, which was approved by the ERCOT Board on November 14, 2006.
Reason: This revision implements the changes to EECP Steps to allow earlier communication of reliability concerns by ERCOT to Market Participants (MPs) and concerned entities.