MIS LOG IN

NPRR042

Summary

Title: Corrections to Section 5, Transmission Security Analysis and Reliability Unit Commitment
Next Group:
Next Step:
Status: Approved on 07/17/2007
Effective Dates:
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (08/01/07 Nodal Protocols Library)

Action

Date Gov Body Action Taken Next Steps
07/17/2007 BOARD Approved
06/28/2007 TAC Recommended for Approval Board consideration of NPRR and IA.
06/12/2007 PRS Recommended for Approval TAC consideration
04/20/2007 PRS Recommended for Approval Impact Analysis review
03/22/2007 PRS Deferred/Tabled

Voting Record

Date Gov Body Motion Result
07/17/2007 BOARD To approve this NPRR as recommended by TAC. Passed
06/28/2007 TAC To recommend approval of NPRR044 and endorse the B1G7 IA as recommended by PRS. Passed
06/12/2007 PRS To endorse the B1G9 IA for NPRR042 as revised by PRS and to forward the documents to TAC. Passed
04/20/2007 PRS To recommend approval of NPRR042 as revised by comments submitted by TPTF. Passed
03/22/2007 PRS Table NPRR042. Passed

Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

Background

Status: Approved
Date Posted: Feb 19, 2007
Sponsor: TPTF
Urgent: No
Sections: 5.6.3, 5.7.1.3, 5.7.2, 5.7.3, 5.7.4.1.1, 5.7.4.1.2, 5.7.4.2, 5.7.5
Description: This NPRR is proposed to change and correct language discovered during TPTF review of the associated business requirements.
Reason: Maintain consistency between business requirements and protocols

Key Documents

Related Content