MIS LOG IN

NOGRR194

Summary

Title Relocate Black Start Training Attendance Requirements to Nodal Operating Guides
Next Group
Next Step
Status Approved on 10/08/2019
Effective Dates
11/01/2019

Action

Date Gov Body Action Taken Next steps
10/08/2019 BOARD Approved
09/25/2019 TAC Recommended for Approval Revision Request Consideration
09/05/2019 ROS Recommended for Approval Revision Request Consideration
08/08/2019 ROS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
10/08/2019 BOARD to approve NOGRR194 as recommended by TAC in the 9/25/19 TAC Report Passed
09/25/2019 TAC to recommend approval of NOGRR194 as recommended by ROS in the 9/5/19 ROS Report Passed
09/05/2019 ROS to endorse and forward to TAC the 8/8/19 ROS Report and the Impact Analysis for NOGRR194 Passed
08/08/2019 ROS to recommend approval of NOGRR194 as amended by the 8/7/19 ERCOT comments Passed

Background

Status: Approved
Date Posted: Jul 24, 2019
Sponsor: ERCOT
Urgent: No
Sections: 1.5.2, 1.5.3, 4.6.4
Description: This Nodal Operating Guide Revision Request (NOGRR) clarifies Black Start training attendance requirements originally located in Nodal Protocol Section 3.14.2, Black Start, and relocates them to the Nodal Operating Guides.
Reason: Market efficiencies or enhancements

Key Documents