MIS LOG IN

NOGRR107

Summary

Title Disturbance Monitoring Requirements Clarification
Next Group
Next Step
Status Approved on 05/02/2013
Effective Dates
06/01/2013

Action

Date Gov Body Action Taken Next steps
05/02/2013 TAC Approved
03/07/2013 TAC Deferred/Tabled TAC Consideration
02/14/2013 ROS Recommended for Approval TAC Consideration
01/28/2013 OWG Recommended for Approval ROS Consideration
12/19/2012 OWG Recommended for Approval OWG IA Review

Voting Record

Date Gov Body Motion Result
05/02/2013 TAC To approve NOGRR107 as recommended by ROS in the 2/14/13 ROS Report. There was one abstention from the Independent Generator Market Segment. All Market Segments were present for the vote Passed
03/07/2013 TAC to table NOGRR107 and to request that the Texas Regional Entity (Texas RE) comment as to how the revisions would apply to existing installations Passed
02/14/2013 ROS To recommend approval of NOGRR107 as recommended by OWG in the 1/28/13 OWG Report and as revised by ROS Passed
01/28/2013 OWG To endorse and forward the 12/19/12 OWG Report and Impact Analysis for NOGRR107 to ROS
12/19/2012 OWG To recommend approval of NOGRR107 as submitted

Background

Status: Approved
Date Posted: Nov 12, 2012
Sponsor: SPWG
Urgent: No
Sections: 6.1.1, 6.1.2, 6.1.2.2, 6.1.2.3, 6.1.2.4, 6.1.4, 6.2.1, 6.2.2
Description: This Nodal Operating Guide Revision Request (NOGRR) clarifies disturbance monitoring requirements.
Reason: Certain disturbance monitoring requirements are vague or unclear and need to be revised to clarify these situations and establish consistency with North American Electric Reliability Corporation (NERC) Reliability Standards in a few areas.

Key Documents