MIS LOG IN

LPGRR041

Summary

Title Distributed Generation (DG) to Sync with NPRR208 Language Effective on Nodal Go-Live
Next Group
Next Step
Status Approved on 11/04/2010
Effective Dates
12/01/2010

Action

Date Gov Body Action Taken Next steps
11/04/2010 TAC Approved
10/07/2010 TAC Recommended for Approval TAC consideration

Voting Record

Date Gov Body Motion Result
11/04/2010 TAC To approve LPGRR041 as recommended by COPS in the 10/12/10 COPS Report Passed
10/07/2010 TAC To recommend approval of LPGRR041 as submitted. Passed

Background

Status: Approved
Date Posted: Sep 23, 2010
Sponsor: Ernie Podraza and Ed Echols on behalf of the Profiling Working Group (PWG)
Urgent: Yes
Sections: Appendix D
Description: This LPGRR removes ‘Renewable’ from the Distributed Renewable Generation criterion for assigning Load Profile Segments that allow for Settlement of excess generation from Electric Service Identifiers (ESI IDs)
Reason: To bring the Load Profiling Guide in agreement with the non-grey-boxed language of NPRR208, Registration and Settlement of Distributed Generation (DG) Less Than One MW.