MIS LOG IN

SMOGRR023

Summary

Title Updates to Nameplate Information Requirements
Next Group
Next Step
Status Approved
Effective Dates
11/01/2020

Action

Date Gov Body Action Taken Next steps
10/28/2020 TAC Recommended for Approval Revision Request Consideration
10/07/2020 WMS Recommended for Approval Revision Request Consideration
09/02/2020 WMS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
10/28/2020 TAC to approve SMOGRR023 as recommended by WMS in the 10/7/20 WMS Report Passed
10/07/2020 WMS to endorse and forward to TAC the 9/2/20 WMS Report and Impact Analysis for SMOGRR023 Passed
09/02/2020 WMS to recommend approval of SMOGRR023 as submitted Passed

Background

Status: Approved
Date Posted: Aug 18, 2020
Sponsor: ERCOT
Urgent: No
Sections: 3.2.3, 7.5.2, and 7.5.6 (delete)
Description: This Settlement Metering Operating Guide Revision Request (SMOGRR) provides an option for certification of nameplates of newly installed or replaced instrument transformers by a professional engineer when nameplate photos cannot be physically accessed because the instrument transformers are installed inside other equipment apparatus, replaces a list of instrument transformer nameplate data requirements with a reference to the Institute of Electrical and Electronics Engineers (IEEE) standards, and deletes Section 7.5.6.
Reason: Addresses current operational issues; Market efficiencies or enhancements

Key Documents