MIS LOG IN

SCR758

Summary

Title Enhancements to the Proposed Transmission Outage Report
Next Group
Next Step
Status Approved on 03/23/2010

Action

Date Gov Body Action Taken Next steps
03/23/2010 BOARD Approved
03/04/2010 TAC Recommended for Approval ERCOT Board for consideration.
02/11/2010 ROS Recommended for Approval TAC for consideration.
01/14/2010 ROS Recommended for Approval ROS for Impact Analysis review.

Voting Record

Date Gov Body Motion Result
03/23/2010 BOARD To approve SCR758 as recommended by TAC in the 3/4/10 TAC Report.
03/04/2010 TAC To recommend approval of SCR758 as recommended by ROS in the 2/11/10 ROS Report. Passed
02/11/2010 ROS To endorse and forward the 1/14/10 ROS Report and the Impact Analysis for SCR758 to TAC. Passed
01/14/2010 ROS To recommend approval of SCR758 as submitted. Passed

Background

Status: Approved
Date Posted: Dec 7, 2009
Sponsor: Mark Garrrett on behalf of Direct Energy
Urgent: No
Sections: Not applicable.
Description: This System Change Request (SCR) proposes to continue to enhance ERCOT’s publishing of transmission Outage details as started with SCR753, Transmission Outage Notice Detail Enhancements, by requesting the publication of additional data which exists in the ERCOT database.
Reason: This SCR enhances transparency of transmission Outages, thus allowing Market Participants to better forecast ERCOT Transmission Grid conditions and improve Operating Plans. SCR753 led to the enhancement of information available in the Approved Transmission Outage report; this SCR expands that same improvement to the companion Proposed Transmission Outage report.

Key Documents

Related Content