PRR722
Summary
| Title | 48 Hour Restoration |
|---|---|
| Next Group | |
| Next Step | |
| Status | Rejected on 05/16/2007 |
Action
| Date | Gov Body | Action Taken | Next Steps |
|---|---|---|---|
| 06/28/2007 | TAC | ||
| 06/21/2007 | PRS | Rejected | Notification to TAC of PRR722's rejection |
| 05/16/2007 | PRS | Rejected | Consideration of request to grant Urgent status |
Voting Record
| Date | Gov Body | Motion | Result |
|---|---|---|---|
| 06/28/2007 | TAC | ||
| 06/21/2007 | PRS | To reject PRR722 | Passed |
| 05/16/2007 | PRS | To grant Urgent status | Failed |
Background
| Status: | Rejected |
|---|---|
| Date Posted: | May 14, 2007 |
| Sponsor: | Dennis Starbuck on behalf of the ERCOT Black Start Task Force |
| Urgent: | No |
| Sections: | 6.5.8, Black Start Service |
| Description: | This Protocol Revision Request (PRR) proposes language so that in the unlikely event of an ERCOT System shut down, ERCOT will return 90% of ERCOT peak load to pre-disturbed condition at or near 48 hours if a viable solution is available. |
| Reason: | This PRR defines a timeline for restoration following a total ERCOT System shut down in the ERCOT Protocols and ERCOT Operating Guides. |
Key Documents
May 14, 2007 - doc - 75.5 KB
May 16, 2007 - xls - 22 KB
May 22, 2007 - doc - 58.5 KB
May 23, 2007 - doc - 56.5 KB
Jun 22, 2007 - doc - 533.5 KB