PGRR140
Summary
Title
Related to NPRR1317, Creation of Non-Settled Generator (NSG) and Clarification of the Types, Usage, and Registration of Distributed Generation
Next Group
ROS
Next Step
ROS for consideration
Status
Pending
Voting Record
Date
Gov Body
Motion
Result
01/08/2026
ROS
To table PGRR140 and refer the issue to the Network Data Support Working Group (NDSWG) and the Planning Working Group (PLWG)
Passed
Background
Status:
Pending
Date Posted:
Dec 19, 2025
Sponsor:
ERCOT
Urgent:
No
Sections:
5.2.1, 5.2.2, 5.2.4, 5.2.9, 5.3.1, 5.3.2, 5.3.2.1, 5.3.2.4.1, 5.3.4, 5.3.5, 5.4.2, and 5.5
Description:
This Planning Guide Revision Request (PGRR) clarifies types and usage of “Distributed Generation” within the Planning Guide in alignment with NPRR1317.
Reason:
Regulatory requirements