Title Update to Standard Generation Interconnection Agreement (SGIA) Requirement
Next Group
Next Step
Status Approved on 03/26/2026

Action

Date Gov Body Action Taken Next Steps
03/26/2026 PUCT Approved
02/09/2026 BOARD Recommended for Approval Revision Request Consideration
01/21/2026 TAC Recommended for Approval Revision Request Consideration
01/08/2026 ROS Recommended for Approval Revision Request Consideration
12/04/2025 ROS Recommended for Approval Impact Analysis Consideration
11/06/2025 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
03/26/2026 PUCT to approve PGRR132 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization. Passed
02/09/2026 BOARD To recommend approval of PGRR132 as recommended by TAC in the 1/21/26 TAC Report Passed
01/21/2026 TAC To recommend approval of PGRR132 as recommended by ROS in the 1/8/26 ROS Report Passed
01/08/2026 ROS To endorse and forward to TAC the 12/4/25 ROS Report and 10/1/25 Impact Analysis for PGRR132 Passed
12/04/2025 ROS to recommend approval of PGRR132 as amended by the 11/25/25 ERCOT comments Passed
11/06/2025 ROS to table PGRR132 and refer the issue to PLWG Passed

Background

Status: Approved
Date Posted: Oct 1, 2025
Sponsor: ERCOT
Urgent: No
Sections: 5.2.8.1
Description: This Planning Guide Revision Request (PGRR) clarifies new Resources must interconnect to the ERCOT System via a new SGIA.
Reason: General system and/or process improvement(s)