Summary

Title Updates to Generation Interconnection or Change Request (GINR) Process
Next Group
Next Step
Status Approved on 08/07/2018
Effective Dates
01/01/2019

Sections 5.2.1, 5.2.2, 5.3, 5.3.1, 5.3.2, 5.4.1, 5.4.2.1, 5.4.7, 5.4.8, 5.4.10, 5.5.4, 5.7.1, 5.7.3, 5.7.4, 5.7.5, 8A, 8B 

03/26/2019

All remaining sections

Action

Date Gov Body Action Taken Next steps
08/07/2018 BOARD Approved
07/26/2018 TAC Recommended for Approval Revision Request Consideration
07/12/2018 ROS Recommended for Approval Revision Request Consideration
06/07/2018 ROS Recommended for Approval Impact Analysis Consideration
04/05/2018 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
08/07/2018 BOARD To approve PGRR062 as recommended by TAC in the 7/26/18 TAC Report. Passed
07/26/2018 TAC To recommend approval of PGRR062 as recommended by ROS in the 7/12/18 ROS Report as revised by TAC. Passed
07/12/2018 ROS To endorse and forward to TAC the 6/7/18 ROS Report, as amended by the 7/3/18 ERCOT comments, and the Impact Analysis for PGRR062. Passed
06/07/2018 ROS To recommend approval of PGRR062 as amended by the 5/21/18 ERCOT comments as revised by ROS. Passed
04/05/2018 ROS To table PGRR062 and refer the issue to the Planning Working Group (PLWG). Passed

Background

Status: Approved
Date Posted: Mar 21, 2018
Sponsor: ERCOT
Urgent: No
Sections: 5.2.1, 5.2.2, 5.3, 5.3.1, 5.3.2, 5.4.1, 5.4.2.1, 5.4.7, 5.4.8, 5.4.10, 5.5.4, 5.7.1, 5.7.2, 5.7.3, 5.7.4, and 5.7.5
Description: This Planning Guide Revision Request (PGRR) proposes new processes, communication, and document sharing and storage requirements to be included in the new Generation Interconnection or Change Request (GINR) application.
Reason: Market efficiencies or enhancements