MIS LOG IN

NPRR988

Summary

Title Correction to Conditions for DAM Award Eligibility for PTP Obligations with Links to an Option
Next Group
Next Step
Status Approved on 02/11/2020
Effective Dates
03/01/2020

Action

Date Gov Body Action Taken Next steps
02/11/2020 BOARD Approved
01/29/2020 TAC Recommended for Approval Revision Request Consideration
12/12/2019 PRS Recommended for Approval Revision Request Consideration

Voting Record

Date Gov Body Motion Result
02/11/2020 BOARD to approve NPRR988 as recommended in the 1/29/20 TAC Report Passed
01/29/2020 TAC to recommend approval of NPRR988 as recommended by PRS in the 12/12/19 PRS Report Passed
12/12/2019 PRS to grant NPRR988 Urgent status; to recommend approval of NPRR988 as submitted, and to forward NPRR988 and the Impact Analysis to TAC Passed

Background

Status: Approved
Date Posted: Dec 11, 2019
Sponsor: ERCOT
Urgent: Yes
Sections: 4.4.6.3
Description: This Nodal Protocol Revision Request (NPRR) allows for the correct and intended implementation of NPRR929 by replacing the word “or” with “and” in paragraph (1)(b)(i) of Section 4.4.6.3 to clarify that both conditions in paragraphs (1)(b)(i) and (1)(b)(ii) of Section 4.4.6.3 are necessary for determining whether a Point-to-Point (PTP) Obligation with Links to an Option bid is eligible to be awarded.
Reason: Other: Conforms Protocol language to intent of NPRR929

Key Documents

Related Content