MIS LOG IN

NPRR707

Summary

Title Provision of Transmission System Voltage Telemetry to QSEs
Next Group
Next Step
Status Withdrawn

Action

Date Gov Body Action Taken Next steps
06/11/2015 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
06/11/2015 PRS To table NPRR707 and refer related issues to ROS. Passed

Background

Status: Withdrawn
Date Posted: May 22, 2015
Sponsor: Luminant
Urgent: No
Sections: 3.10.7.5.2
Description: This Nodal Protocol Revision Request (NPRR) requires ERCOT to provide, upon request, transmission system voltage at each Generation Resource Point of Interconnection (POI) to the transmission system through telemetry via Inter-Control Center Communications Protocol (ICCP). This is necessary for the Generation Resource to comply with the latest version of North American Electric Reliability Corportation (NERC) Standard VAR-002-3, Generator Operation for Maintaining Network Voltage Schedules. Paragraph R2, 2.3, requires generation operators to monitor the voltage at the location specified in their voltage schedule. This data is readily available from ERCOT and provision of this data should not violate any of the provisions of Nodal Protocol Section 1.3, Confidentiality.
Reason: Regulatory requirements

Key Documents

Related Content