NPRR462

Summary

Title Removal of Consumer Benefit Test from the ERCOT Planning Criteria
Next Group
Next Step
Status Approved on 07/17/2012
Effective Dates
08/01/2012

Action

Date Gov Body Action Taken Next steps
07/17/2012 BOARD Approved
06/28/2012 TAC Recommended for Approval ERCOT Board Consideration
06/21/2012 PRS Recommended for Approval TAC for consideration.
05/17/2012 PRS Recommended for Approval PRS IA Review

Voting Record

Date Gov Body Motion Result
07/17/2012 BOARD To approve NPRR462 as recommended by TAC in the 6/28/12 TAC Report. Passed
06/28/2012 TAC To recommend approval of NPRR462 as recommended by PRS in the 6/21/12 PRS Report Passed
06/21/2012 PRS To endorse and forward the 5/17/12 PRS Report and Impact Analysis for NPRR462 to TAC. Passed
05/17/2012 PRS To recommend approval of NPRR462 as amended by the 5/16/12 Oncor comments and as revised by PRS Passed

Background

Status: Approved
Date Posted: May 2, 2012
Sponsor: ERCOT
Urgent: No
Sections: 3.11.2
Description: This Nodal Protocol Revision Request (NPRR) removes the consumer benefit test from the ERCOT planning criteria consistent with the Public Utility Commission of Texas (PUCT) Project 39537, Rulemaking to Implement HB 971, Relating to Economic Criteria for a Certificate of Convenience and Necessity for an Electric Transmission Project.
Reason: PUCT Project 39537 removed the consumer benefit test from P.U.C. Subst. R. 25.101, Certification Criteria, and therefore should be removed from the ERCOT planning criteria for consistency.