MIS LOG IN

NPRR452

Summary

Title Clarification of Reactive Power Requirements
Next Group
Next Step
Status Approved on 07/17/2012
Effective Dates
08/01/2012

Action

Date Gov Body Action Taken Next steps
07/17/2012 BOARD Approved
06/07/2012 TAC Recommended for Approval ERCOT Board Consideration
05/17/2012 PRS Recommended for Approval TAC Consideration
04/19/2012 PRS Recommended for Approval PRS IA Review

Voting Record

Date Gov Body Motion Result
07/17/2012 BOARD To approve NPRR452 as recommended by TAC in the 6/7/12 TAC Report. Passed
06/07/2012 TAC To recommend approval of NPRR452 as recommended by PRS in the 5/17/12 PRS Report and as revised by TAC Passed
05/17/2012 PRS To endorse and forward the 4/19/12 PRS Report and Impact Analysis for NPRR452 to TAC Passed
04/19/2012 PRS To approve NPRR452 as amended by the 4/18/12 ERCOT comments Passed

Background

Status: Approved
Date Posted: Mar 23, 2012
Sponsor: John Adams on behalf of the NPRR366 Workshop
Urgent: No
Sections: 3.15
Description: This Nodal Protocol Revision Request (NPRR) clarifies the Reactive Power requirement for Generation Resources required to provide Voltage Support Service (VSS).
Reason: On March 14, 2012, participants of the NPRR366 Workshop identified that clarification of the Reactive Power Requirements for applicable Generation Resources is necessary and therefore should be addressed in a new NPRR intended to replace NPRR366, Generation Resource Power Factor Criteria Clarification which was withdrawn on April 16, 2012.

Key Documents

Related Content