MIS LOG IN

NPRR242

Summary

Title Synchronization of Nodal Protocols with PRR792
Next Group
Next Step
Status Approved on 08/17/2010
Effective Dates
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (09/01/10 Nodal Protocols Library)

Action

Date Gov Body Action Taken Next steps
08/16/2010 BOARD Approved
08/17/2010 BOARD Approved
08/05/2010 TAC Recommended for Approval ERCOT Board for consideration.
06/17/2010 PRS Recommended for Approval PRS for Impact Analysis review.
07/22/2010 PRS Recommended for Approval TAC for consideration.

Voting Record

Date Gov Body Motion Result
08/16/2010 BOARD To approve NPRR242 as amended by the 8/9/10 ERCOT comments Passed
08/17/2010 BOARD To approve NPRR242 as recommended by TAC in the 8/5/10 TAC Report. Passed
08/05/2010 TAC To recommend approval of NPRR242 as recommended by PRS in the 7/22/10 PRS Report. Passed
06/17/2010 PRS To recommend approval of NPRR242 as submitted. Passed
07/22/2010 PRS To endorse and forward the 6/17/10 PRS Report and the Impact Analysis for NPRR242 to TAC.

Background

Status: Approved
Date Posted: Jun 1, 2010
Sponsor: ERCOT
Urgent: No
Sections: 1.3.1.1, 14.2, 14.5.2, 14.5.3 (new), 14.9.3.1, 14.9.5
Description: This Nodal Protocol Revision Request (NPRR) synchronizes the Nodal Protocols with Protocol Revision Request (PRR) 792, Revised Renewable Portfolio Standards Allocation Process, Pursuant to P.U.C. Subst. R. 25.173, approved by the ERCOT Board on January 20, 2009.
Reason: To synchronize the Nodal Protocols with PRR792.

Key Documents

Related Content