MIS LOG IN

NPRR002

Summary

Title Section 3, Zonal PRR Synchronization and ERCOT Staff Clarifications
Next Group
Next Step
Status Approved on 08/15/2006
Effective Dates
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (09/01/06 Nodal Protocols Library)

Action

Date Gov Body Action Taken Next steps
07/17/2007 BOARD Approved
06/28/2007 TAC Recommended for Approval Review of B1G6 Impact Analysis
06/12/2007 PRS Recommended for Approval Review of B1G6 Impact Analysis
08/15/2006 BOARD Approved
08/03/2006 TAC Recommended for Approval Board consideration
07/20/2006 PRS Recommended for Approval TAC review
07/11/2006 TPTF Recommended for Approval PRS review
06/22/2006 PRS Referred TPTF and ROS review.

Voting Record

Date Gov Body Motion Result
07/17/2007 BOARD To approve the B1G6 Impact Analysis as recommended by TAC. Passed
06/28/2007 TAC Recommend approval of the B1G6 IA as recommended by PRS. Passed
06/12/2007 PRS Endorse the B1G6 IA as revised by PRS and forward the document to TAC for approval. Passed
08/15/2006 BOARD On 8/15/06, the Board voted to approve NPRR002 as recommended by TAC Passed
08/03/2006 TAC To recommend approval as recommended by PRS. Passed
07/20/2006 PRS To recommend approval as ammended by TPTF. Passed
07/11/2006 TPTF
06/22/2006 PRS Refer to TPTF and ROS to review NDSWG and ERCOT Staff comments. Passed

Background

Status: Approved
Date Posted: May 19, 2006
Sponsor: TPTF
Urgent: No
Sections: 3
Description: This NPRR incorporates relevant language from the following PRRs that were approved by the Board between April 2004 and February 2006: PRR492, Plan to Alleviate Chronic Local Congestion; PRR513, Verification of Operational Model after Recurring Local Congestion Event; PRR576, Disclosure of OOME, OOMC, and RMR Service; PRR596, Mothballed Generation Resource Estimated Return to Service Dates/PRR573, Mothballed Generation Resource Definition and Time to Service Updates; PRR581, Update RMR Language Due to PUC Rule 25.502; PRR627, RMR Transmission Issues and RMR Contract Extension; and PRR633, TSP Data Information Requirements. PRR307, Controllable Resources, was part of the TNT synchronization because a portion of the PRR language in the current zonal protocols was inadvertently not included in the nodal protocols section 3.17.2(2). This NPRR also incorporates TPTF determinations regarding ERCOT Staff clarification questions as documented in the ERCOT Clarification Matrix for Section 3 and discussed by TPTF and 3/29/06, 4/10/06 and 4/11/06.
Reason: To incorporate into the Draft Nodal Protocols provisions approved by the Board for the Zonal market and determined by the ERCOT stakeholders to be relevant to the Nodal market.

Key Documents

Related Content