NOGRR279

Summary

Title Deadline Extensions for Recording Equipment Installation
Next Group TAC
Next Step Revision Request Consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
10/02/2025 ROS Recommended for Approval Revision Request Consideration
09/11/2025 ROS Recommended for Approval Impact Analysis Consideration
08/07/2025 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
10/02/2025 ROS to endorse and forward to TAC the 9/11/25 ROS Report and 9/24/25 Impact Analysis for NOGRR279 Passed
09/11/2025 ROS to recommend approval of NOGRR279 as amended by the 8/28/25 ERCOT comments Passed
08/07/2025 ROS to table NOGRR279 Passed

Background

Status: Pending
Date Posted: Jul 23, 2025
Sponsor: Invenergy
Urgent: No
Sections: 6.1.4
Description: This Nodal Operating Guide Revision Request (NOGRR) modifies the monitoring equipment installation deadlines established by NOGRR255, High Resolution Data Requirements, to January 1, 2029 in a manner consistent with North American Electric Reliability Corporation (NERC) Reliability Standard, PRC-028-01, Disturbance Monitoring and Reporting Requirements for Inverter-Based Resources. This language also clarifies that synchronized resources that have Standard Generation Interconnection Agreements (SGIAs) executed prior to July 25, 2024 (the date in which the Public Utility Commission of Texas (PUCT) approved NOGRR255) have 12 months beyond their Commercial Operations Date to comply with the new equipment standards.
Reason: Strategic Plan Objective 1 – Be an industry leader for grid reliability and resilience