MIS LOG IN

NOGRR122

Summary

Title CRR Network Model Clarification for Accepted Outages
Next Group
Next Step
Status Approved on 12/03/2013
Effective Dates
01/01/2014

Action

Date Gov Body Action Taken Next steps
12/03/2013 TAC Approved
11/14/2013 ROS Recommended for Approval TAC for consideration
10/16/2013 OWG Recommended for Approval ROS for consideration
09/18/2013 OWG Recommended for Approval OWG IA Review

Voting Record

Date Gov Body Motion Result
12/03/2013 TAC To approve NOGRR122 as recommended by ROS in the 11/14/13 ROS Report Passed
11/14/2013 ROS To recommend approval of NOGRR122 as recommended by OWG in the 10/16/13 OWG Report. Passed
10/16/2013 OWG To endorse and forward the 9/18/13 OWG Report and Impact Analysis for NOGRR122 to ROS. Passed
09/18/2013 OWG To recommend approval of NOGRR122 as submitted. Passed

Background

Status: Approved
Date Posted: Aug 16, 2013
Sponsor: ERCOT
Urgent: No
Sections: 5.1
Description: This Nodal Operating Guide Revision Request (NOGRR) aligns the Operating Guides with current practice by clarifying that "approved" as well as "accepted" Transmission Outages in the Outage Scheduler are utilized in ERCOT’s Congestion Revenue Rights (CRR) Auction at the time of building the CRR Network Model.
Reason: To align the Operating Guides with current ERCOT practice.