MIS LOG IN

NOGRR060

Summary

Title Updating the Term Resource Plan to Current Operating Plan
Next Group
Next Step
Status Approved on 06/02/2011
Effective Dates
07/01/2011

Action

Date Gov Body Action Taken Next steps
06/02/2011 TAC Approved
05/12/2011 ROS Recommended for Approval TAC consideration
04/20/2011 OWG Recommended for Approval ROS consideration
03/07/2011 OWG Recommended for Approval OWG review the IA.

Voting Record

Date Gov Body Motion Result
06/02/2011 TAC To approve NOGRR060 as recommended by ROS in the 5/12/11 ROS Report Passed
05/12/2011 ROS To recommend approval of NOGRR060 as recommended by OWG in the 4/20/11 OWG Report. Passed
04/20/2011 OWG Consensus to endorse and forward the 3/7/11 OWG Report and Impact Analysis for NOGRR060 to ROS. Passed
03/07/2011 OWG In consensus to recommend approval of NOGRR060 as submitted. Passed

Background

Status: Approved
Date Posted: Feb 1, 2011
Sponsor: Luminant Energy
Urgent: No
Sections: 4.5.3.2
Description: This Nodal Operating Guide Revision Request (NOGRR) replaces the term "Resource Plan" with the term"Current Operating Plan" in the instance where the change in terminology was not previously made.
Reason: Corrects terminology used in the Nodal Operating Guide.

Key Documents