Summary

Title Synchronization of OGRR198, Firm Load Shed Implementation Time Periods
Next Group
Next Step
Status Approved on 08/07/2008
Effective Dates
09/01/2008

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (09/01/08 Nodal Operating Guide Library)

Action

Date Gov Body Action Taken Next steps
08/07/2008 TAC Approved
07/10/2008 ROS Recommended for Approval
06/18/2008 OWG Recommended for Approval ROS Consideration
05/21/2008 OWG Recommended for Approval Impact Analysis Review

Voting Record

Date Gov Body Motion Result
08/07/2008 TAC To approve NOGRR020 as recommended by ROS. Passed
07/10/2008 ROS To recommend approval of NOGRR020 as recommended by OWG. Passed
06/18/2008 OWG Consensus to forward the OWG Recommendation Report and Impact Analysis to ROS for approval Passed
05/21/2008 OWG Consensus to recommend approval of NOGRR020 as submitted. Passed

Background

Status: Approved
Date Posted: Apr 16, 2008
Sponsor: OGRTF
Urgent: No
Sections: 4.5.3
Description: This Nodal Operating Revision Request (NOGRR) incorporates relevant language from OGRR198 which was approved by TAC on 03/06/08.
Reason: To incorporate into the Nodal Operating Guides provisions approved by TAC for the Zonal market and determined by the ERCOT stakeholders to be relevant to the Nodal market.