Summary
| Title | Revised DNP Process Necessary for PUCT Project 29637 | 
|---|---|
| Next Group | |
| Next Step | |
| Status | Approved on 12/01/2006 | 
| Effective Dates | 06/25/2007 | 
Action
| Date | Gov Body | Action Taken | Next Steps | 
|---|---|---|---|
| 12/01/2006 | TAC | Approved | |
| 11/08/2006 | RMS | Recommended for Approval | |
| 10/11/2006 | RMS | Recommended for Approval | Impact Analysis Review | 
Voting Record
| Date | Gov Body | Motion | Result | 
|---|---|---|---|
| 12/01/2006 | TAC | Approve RMGRR045 as recommended by RMS | Passed | 
| 11/08/2006 | RMS | Recommend approval of the RMS Recommendation Report and endorse the Impact Analysis | Passed | 
| 10/11/2006 | RMS | Recommend approval of RMGRR045 as revised by RMS and Direct Energy comments. | Passed | 
Background
| Status: | Approved | 
|---|---|
| Date Posted: | Sep 6, 2006 | 
| Sponsor: | Terms and Conditions Task Force | 
| Urgent: | No | 
| Sections: | 7.6 | 
| Description: | Revise the Disconnect for Non-Pay (DNP) process as currently documented in the Retail Market Guide in order to comply with the Terms & Conditions Tariff. Changes include: 1) Changing the Section Title to clarify this is the DNP Process 2) Clarify timelines for submitting and completing disconnects and reconnects | 
| Reason: | New Terms & Conditions necessitates changes to the process as currently detailed in the Retail Market Guide. | 