MIS LOG IN

PRR728

Summary

Title Proposal to Allow ERCOT Discretion When Processing Renewable Production Values
Next Group
Next Step
Status Approved on 07/19/2007

Action

Date Gov Body Action Taken Next steps
08/21/2007 BOARD Approved
08/02/2007 TAC Recommended for Approval Board consideration of PRR728.
07/19/2007 PRS Approved TAC consideration of PRR728.
06/21/2007 PRS Deferred/Tabled PRS consideration

Voting Record

Date Gov Body Motion Result
08/21/2007 BOARD Approve as recommended by TAC. Passed
08/02/2007 TAC To recommend approval of PRR728 as revised by TAC. Passed
07/19/2007 PRS To grant the request for Urgent status for PRR728. Passed
06/21/2007 PRS To table PRR728 until next month. Passed

Background

Status: Approved
Date Posted: May 25, 2007
Sponsor: ERCOT Staff
Urgent: No
Sections: 6.8.1.15.1, Uninstructed Resource Charge Process
Description: This PRR modifies paragraph (3) of Section 6.8.1.15.1 to allow ERCOT the discretion to process Renewable Production Potential values when submitted by Qualified Scheduling Entities (QSEs) representing only Uncontrollable Renewable Resources.
Reason: Over the last several months, ERCOT has collected, on average, $11,000 in URC from QSEs submitting Renewable Production Potential values. To process these data, ERCOT uses contractors at an average cost of $4,000 per month. Through this PRR, ERCOT requests the discretion to not process these Renewable Production Potential values and not calculate Uninstructed Deviation Pricing for QSEs that submit such data. Eliminating this manual process will free these contract resources to work on nodal implementation and other matters.