Title Large Load Interconnection Queue Process Revision
Next Group ROS
Next Step ROS for consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
No updates have been made to this issue.

Voting Record

Date Gov Body Motion Result
No updates have been made to this issue.

Background

Status: Pending
Date Posted: Nov 4, 2025
Sponsor: Cholla Petroleum
Urgent: Pending
Sections: 9.3.4.1
Description: This Planning Guide Revision Request (PGRR) changes the criteria of the Large Load Interconnection Study (LLIS) process to use demonstrated financial commitment in place of signed Load interconnection as a requirement for advancement.
Reason: Strategic Plan Objective 2

Key Documents