MIS LOG IN

NPRR808

Summary

Title Three Year CRR Auction
Next Group
Next Step
Status Approved on 04/04/2017
Effective Dates
09/01/2017

Action

Date Gov Body Action Taken Next steps
04/04/2017 BOARD Approved
03/23/2017 TAC Recommended for Approval Board for consideration
02/09/2017 PRS Recommended for Approval TAC for consideration
01/19/2017 PRS Recommended for Approval PRS for Impact Analysis review
12/01/2016 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
04/04/2017 BOARD To approve NPRR808 as recommended by TAC in the 3/23/17 TAC Report Passed
03/23/2017 TAC To recommend approval of NPRR808 as recommended by PRS in the 2/9/17 PRS Report Passed
02/09/2017 PRS To endorse and forward to TAC the 1/19/17 PRS Report and Impact Analysis for NPRR808 with a recommended priority of 2017 and rank of 1930 Passed
01/19/2017 PRS To recommend approval of NPRR808 as amended by the 1/18/17 DC Energy comments Passed
12/01/2016 PRS To table NPRR808 and refer the issue to WMS Passed

Background

Status: Approved
Date Posted: Nov 15, 2016
Sponsor: Morgan Stanley Capital Group, Inc
Urgent: No
Sections: 2.1, 3.4.2, 3.4.3, and 7.5.1
Description: This Nodal Protocol Revision Request (NPRR) extends the Congestion Revenue Right (CRR) Auction process into the third year forward; revises the percentages sold in the CRR Long-Term Auction Sequence; and makes aligning changes to the timetable for modifying Load Zones.
Reason: Market efficiencies or enhancements

Key Documents

Related Content