This Nodal Operating Guide Revision Request (NOGRR) aligns criteria for Large Computational Loads (LCL) to be exempt from the frequency and voltage ride-through requirements that were approved in NOGRR282, Board Priority - Large Computational Load Ride-Through Requirements, with the eligibility criteria for inclusion in Batch Zero introduced in Planning Guide Revision Request (PGRR) 145, Batch Zero Process for Large Load Interconnections. In order to be exempt from frequency and voltage ride-through requirements, the LCL must also have been included in Batch Zero as base load in accordance with Planning Guide Section 9.2.1.1 Eligibility Criteria for Inclusion of a Large Load as Base Load not Subject to Additional Study in the Batch Zero Process.