MIS LOG IN

NOGRR088

Summary

Title Synchronization with NPRR424, Reactive Capability Testing Requirements for IRRs
Next Group
Next Step
Status Approved on 06/07/2012
Effective Dates
07/01/2012

Action

Date Gov Body Action Taken Next steps
06/07/2012 TAC Approved
04/05/2012 TAC Deferred/Tabled TAC Consideration
03/08/2012 ROS Recommended for Approval TAC Consideration
02/15/2012 OWG Recommended for Approval ROS Consideration
01/30/2012 OWG Recommended for Approval OWG IA Review

Voting Record

Date Gov Body Motion Result
06/07/2012 TAC To approve NOGRR088 as recommended by ROS in the 3/8/12 ROS Report with an effective date of July 1, 2012 Passed
04/05/2012 TAC To table NOGRR088 for one month Passed
03/08/2012 ROS To recommend approval of NOGRR088 as recommended by OWG in the 2/15/12 OWG Report. Passed
02/15/2012 OWG Consensus to endorse and forward the 1/30/12 OWG Report and Impact Analysis to ROS
01/30/2012 OWG Consensus to recommend approval of NOGRR088 as revised by OWG

Background

Status: Approved
Date Posted: Dec 12, 2011
Sponsor: ERCOT
Urgent: No
Sections: 3.3.2.2, 3.3.2.3
Description: This Nodal Operating Guide Revision Request (NOGRR) synchronizes the Nodal Operating Guides with Nodal Protocol Revision Request (NPRR) 424 which defines the reactive capability testing requirement for Intermittent Renewable Resources (IRRs).
Reason: To synchronize the Nodal Operating Guides with NPRR424.

Key Documents