1.

Antitrust Admonition


9:30 a.m.

2.

Miscellaneous Updates

ERCOT

9:35 a.m.

3.

EIR Status Update – Childress Area Transmission Improvement Project

ERCOT

9:40 a.m.

4.

EIR Status Update – Combined CPS Energy Reactive Power Planning Project & CPS Energy Helotes 345/138-kV Switching Station and Autotransformer Addition at Eastside Switching Station Project

ERCOT

9:50 a.m.

5.

EIR Status Update – Ammonia Plant Load Project

ERCOT

10:00 a.m.

6.

EIR Status Update – Nueces Green Ammonia Load Interconnection Project

ERCOT

10:10 a.m.

7.

EIR Status Update – Muscovy and Voss Lake 345/138-kV Project

ERCOT

10:20 a.m.

8.

EIR Status Update – Connell 345/138-kV Switch and Connell to Rockhound 345-kV Double-Circuit Line Project

ERCOT

10:30 a.m.

9.

EIR Status Update – P.H. Robinson to W.A. Parish 345-kV Hardening Project

ERCOT

10:40 a.m.

10.

EIR Status Update – Texas 765-kV-STEP Eastern Backbone Project

ERCOT

11:00 a.m.

11.

EIR Status Update – Drill Hole to Sand Lake to Solstice 765-kV Line Project

ERCOT

11:10 a.m.

12.

Skyview 345/138-kV Switch Project Overview

Oncor

11:20 a.m.

13.

ERCOT Independent Review Scope: Skyview 345/138-kV Switch Project

ERCOT

11:30 a.m.

14.

2025 RTP Economic Analysis Update

ERCOT

11:40 a.m.

15.

Adjourn