MIS LOG IN

Southern Cross Transmission - Directive 11

Title: Determination regarding allocation of costs identified in PUC Docket No. 45624
Status: Complete
Description: As ordered by the Public Utility Commission of Texas (PUCT) in Project No. 46304: ERCOT shall study and recommend appropriate responsibility for, and allocation of, the costs identified in the Commission's final order in Docket No. 45624, including costs common to the ERCOT system and special costs that are specific to the Garland line and Southern Cross DC tie, and shall identify any existing protocols that need to be modified or new protocols that need to be created, or (if appropriate) any existing Commission rules that need to be modified or new rules that need to be enacted, to appropriately address those costs.