MIS LOG IN

RMGRR037

Summary

Title Submission of Switch Requests during a Mass Transition Event
Next Group
Next Step
Status Approved on 06/14/2006
Effective Dates
08/01/2006

Action

Date Gov Body Action Taken Next steps
07/06/2006 TAC Approved
06/14/2006 RMS Approved

Voting Record

Date Gov Body Motion Result
07/06/2006 TAC Unanimous Passed
06/14/2006 RMS On 06/14/06, RMS unanimously voted to recommend approval of RMGRR037 as submitted. All Market Segments were present. Passed

Background

Status: Approved
Date Posted: May 31, 2006
Sponsor: Kathy Scott on behalf of TX SET
Urgent: Yes
Sections: 7.11.5.2.2 Scenario Two: A Date Certain Transition (Off-Cycle) With Either Full or Partial Cooperation from the Losing Competitive Retailer 7.11.7 Competitive Retailer Transition Assumptions
Description: This PRR introduces revisions to Section 7.11, Mass Customer Transition Process. Several sections were updated, modified and some areas language was deleted where needed in the Retail Market Guide (RMG) to reflect current Market processes and procedures during a mass transition event.
Reason: To support the changes submitted in PRR670, First Available Switch Date (FASD) for Switch Requests where Customer no notification is required based upon the event and PUCT Rules, the current Retail Market Guide (RMG) Section 7.11, Mass Customer Transition Process would also require changes to bring both documents in line preventing any discrepancies or issues.

Key Documents