MIS LOG IN

PRR713

Summary

Title Resource Outage Notification
Next Group
Next Step
Status Approved on 09/18/2007
Effective Dates
10/01/2007

Action

Date Gov Body Action Taken Next steps
09/18/2007 BOARD Approved
08/02/2007 TAC Recommended for Approval Board of Directors consideration of this PRR
07/19/2007 PRS Recommended for Approval TAC consideration of this PRR
06/21/2007 PRS Recommended for Approval PRS consideration of Impact Analysis
03/22/2007 PRS Deferred/Tabled PRS consideration

Voting Record

Date Gov Body Motion Result
09/18/2007 BOARD To approve this PRR as recommended by the TAC Passed
08/02/2007 TAC To recommend approval of PRR713 as recommended by PRS Passed
07/19/2007 PRS To forward the PRS Recommendation Report and IA to TAC. Passed
06/21/2007 PRS To recommend approval of PRR713 initial language Passed
03/22/2007 PRS Table Passed

Background

Status: Approved
Date Posted: Feb 21, 2007
Sponsor: ERCOT Staff
Urgent: No
Sections: 6.5.9, Reliability Must-Run Service; 6.5.9.1, Initiation and Approval of RMR Agreements; 6.5.9.3, Mothballed Generation Resource Time to Service Updates; 8.4, Acceptance of Proposed Planned Outages of Resources other than Reliability Resources; Section 22, Attachment I: Notification of Suspension of Operations; Section 22, Attachment F: Standard Form Reliability Must-Run Agreement; Section 22, Attachment K: Notification of Change of Generation Resource Designation (New)
Description: This PRR clarifies and further details the long-term outage notification submission process for resources.
Reason: To clarify and expand explanation options for long-term outages. This is necessary for ERCOT and Transmission and Distribution Service Provider (TDSP) modeling accuracy so that the transmission system can be planned and operated reliably.

Key Documents

Related Content