MIS LOG IN

LPGRR012

Summary

Title Process for Load Profiling Guide Revisions
Next Group
Next Step
Status Approved on 07/06/2006
Effective Dates
08/01/2006

Action

Date Gov Body Action Taken Next steps
07/06/2006 TAC Approved
06/27/2006 COPS Recommended for Approval

Voting Record

Date Gov Body Motion Result
07/06/2006 TAC Approve as recommended by COPS. Passed
06/27/2006 COPS Motion to recommend for approval Passed

Background

Status: Approved
Date Posted: May 2, 2006
Sponsor: ERCOT
Urgent: No
Sections: Section 2, Appendix A
Description: This revision will replace the current Change Control Process in Section 2, Change Control. Specifically, this LPGRR: Adds an Impact Analysis requirement to Load Profiling Guide Revision Process. Allows the submitter to withdraw a LPGRR only before PWG issues a recommendation. Allows COPS to reject a LPGRR and notify TAC, rather than recommend a rejection to TAC. Clarifies that if PWG cannot reach a consensus on a LPGRR, COPS is required to resolve the issue. Requires ERCOT Board approval of LPGRRs with an ERCOT system or staffing impact. Authorizes ERCOT staff to implement Administrative LPGRRs. Outlines the process to appeal a decision.
Reason: The current Change Control Process documented in the Load Profiling Guide is not consistent with Protocol Section 21, Process for Protocol Revision. Consistency with the Protocols and other market guides will simplify and clarify the process, as well as create transparency for all Market Participants.

Key Documents