Sep 11, 2025 3:51:11 PM ERCOT will be working from the alternate control center until further notice, use the OPX numbers for Bastrop. Operational Information Active
Sep 11, 2025 12:36:15 PM At 12:35, ERCOT ended the RTC+B closed loop test and is currently operating back on Production Energy & Market Management Systems. Operational Information Active
Sep 11, 2025 12:00:18 PM At 12:35, ERCOT plans to end the RTC+B closed loop test and cutover its Energy & Market Management Systems back to Production systems. Operational Information Active
Sep 11, 2025 10:38:49 AM At 10:35, ERCOT initiated a RTC+B closed loop test and is currently operating on RTC+B Energy & Market Management Systems. Operational Information Active
Sep 11, 2025 10:00:09 AM At 10:35, ERCOT plans to perform a RTC+B closed loop test and cutover of its Energy & Market Management Systems to RTC+B systems. Operational Information Active
Sep 11, 2025 8:47:26 AM The Daily RSASM for 09/11/2025 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 11, 2025 12:00:33 AM No sudden loss of generation greater than 450 MW occurred on September 10, 2025. Operational Information Active
Sep 10, 2025 8:46:31 AM The Daily RSASM for 09/10/2025 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 10, 2025 2:00:57 AM ERCOT has cancelled the following notice: ERCOT will execute a SASM at 01:35 for operating day 9/10/25 this is for ECRS HE13 28.5MW HE17 26.9MW NONSPIN HE13 10.6MW HE14 7MW RRS HE8 35.3MW HE10 56MW HE12 56MW. Operational Information Cancelled
Sep 10, 2025 1:09:03 AM ERCOT will execute a SASM at 01:35 for operating day 9/10/25 this is for ECRS HE13 28.5MW HE17 26.9MW NONSPIN HE13 10.6MW HE14 7MW RRS HE8 35.3MW HE10 56MW HE12 56MW. Operational Information Active
Sep 10, 2025 12:05:13 AM No sudden loss of generation greater than 450 MW occurred on September 9, 2025. Operational Information Active
Sep 9, 2025 8:46:35 AM The Daily RSASM for 09/09/2025 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 9, 2025 12:09:26 AM No sudden loss of generation greater than 450 MW occurred on September 8, 2025. Operational Information Active
Sep 8, 2025 8:46:12 AM The Daily RSASM for 09/08/2025 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 8, 2025 12:00:39 AM No sudden loss of generation greater than 450 MW occurred on September 7, 2025. Operational Information Active
Sep 7, 2025 8:46:08 AM The Daily RSASM for 09/07/2025 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 7, 2025 12:01:41 AM No sudden loss of generation greater than 450 MW occurred on September 6, 2025. Operational Information Active
Sep 6, 2025 8:46:15 AM The Daily RSASM for 09/06/2025 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 6, 2025 12:01:47 AM No sudden loss of generation greater than 450 MW occurred on September 5, 2025. Operational Information Active
Sep 5, 2025 8:54:29 AM ERCOT has cancelled the following notice: ERCOT is taking manual actions to pre-posture for a planned outage in the Del Rio region. Operational Information Cancelled
Sep 5, 2025 8:46:28 AM The Daily RSASM for 09/05/2025 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 5, 2025 7:59:43 AM ERCOT is taking manual actions to pre-posture for a planned outage in the Del Rio region. Operational Information Active
Sep 5, 2025 12:03:20 AM No sudden loss of generation greater than 450 MW occurred on September 4, 2025. Operational Information Active
Sep 4, 2025 8:21:28 PM At 20:20, All Non-Spin has been recalled. Operational Information Active
Sep 4, 2025 8:20:00 PM CM-ASM-NOTF AS_TYPE: Non-Spin, DEPLOY_MW: 0.0, BEGIN_TIME: 2025-09-04 20:20:00, END_TIME: 2025-09-04 20:20:00, DURATION: 0 Hrs 0 Mins.; Operational Information
Sep 4, 2025 7:33:01 PM CM-ASM-NOTF AS_TYPE: Non-Spin, DEPLOY_MW: 1031.1, BEGIN_TIME: 2025-09-04 20:00:00, END_TIME: 2025-09-04 23:59:01, DURATION: 3 Hrs 59 Mins.; Operational Information
Sep 4, 2025 6:51:42 PM At 18:50 approximately 965.2 MW of Non-Spin has been deployed, anticipated duration is 23:59:01. Operational Information Active
Sep 4, 2025 6:50:14 PM CM-ASM-NOTF AS_TYPE: Non-Spin, DEPLOY_MW: 965.2, BEGIN_TIME: 2025-09-04 18:50:13, END_TIME: 2025-09-04 23:59:01, DURATION: 5 Hrs 8 Mins.; Operational Information
Sep 4, 2025 3:51:03 PM ERCOT Emergency Base Points are Disabled Operational Information Cancelled
Sep 4, 2025 3:42:23 PM ERCOT Emergency Base Points are Enabled Operational Information Active
Sep 4, 2025 11:41:47 AM At 3:30 PM on 9/04/2025, ERCOT will perform site failover of its Energy & Market Management Systems. During this time, market communications will be unavailable for about 20 minutes, and real-time communications will be unavailable for about 5 minutes. All systems should re-establish communications automatically. This event will be preceded by a "hot line" call shortly before beginning. Operational Information Active
Sep 4, 2025 8:46:17 AM The Daily RSASM for 09/04/2025 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 4, 2025 12:20:53 AM No sudden loss of generation greater than 450 MW occurred on September 3, 2025. Operational Information Active
Sep 3, 2025 9:58:57 AM The DC_E (East) DC Tie will be unavailable from 11/04/2024 14:17 through 09/26/2025 16:00 due to a forced outage. Operational Information Active
Sep 3, 2025 8:46:51 AM The Daily RSASM for 09/03/2025 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 3, 2025 12:16:42 AM No sudden loss of generation greater than 450 MW occurred on September 2, 2025. Operational Information Active
Sep 2, 2025 8:46:22 AM The Daily RSASM for 09/02/2025 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 2, 2025 12:07:47 AM No sudden loss of generation greater than 450 MW occurred on September 1, 2025. Operational Information Active
Sep 1, 2025 8:46:18 AM The Daily RSASM for 09/01/2025 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 1, 2025 12:18:29 AM No sudden loss of generation greater than 450 MW occurred on August 31, 2025. Operational Information Active