MIS LOG IN

NPRR941

Summary

Title Create a Lower Rio Grande Valley Hub
Next Group
Next Step
Status Approved on 12/10/2019

Action

Date Gov Body Action Taken Next steps
12/10/2019 BOARD Approved
11/20/2019 TAC Recommended for Approval Board for consideration
11/13/2019 PRS Recommended for Approval TAC for consideration
10/10/2019 PRS Deferred/Tabled PRS for consideration
09/12/2019 PRS Deferred/Tabled PRS for consideration
08/15/2019 PRS Recommended for Approval PRS for Impact Analysis consideration
06/13/2019 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
12/10/2019 BOARD To approve NPRR941 as recommended by TAC in the 11/20/19 TAC Report Passed
11/20/2019 TAC To recommend approval of NPRR941 as recommended by PRS in the 11/13/19 PRS Report as revised by TAC, and the Revised Impact Analysis Passed
11/13/2019 PRS To endorse and forward to TAC the 8/15/19 PRS Report as amended by the 10/28/19 ERCOT comments and the Impact Analysis for NPRR941 with a recommended priority of 2020 and rank of 2860 Passed
10/10/2019 PRS To table NPRR941 Passed
09/12/2019 PRS To table NPRR941 for one month Passed
08/15/2019 PRS To recommend approval of NPRR941 as amended by the 8/6/19 DC Energy comments Passed
06/13/2019 PRS To table NRR941 and refer the issue to WMS Passed

Background

Status: Approved
Date Posted: May 7, 2019
Sponsor: DC Energy
Urgent: No
Sections: 3.5.2.6 (new), 3.5.2.6, and 3.5.2.7
Description: This Nodal Protocol Revision Request (NPRR) creates a trading Hub “Lower Rio Grande Valley 138/345 kV Hub (LRGV 138/345)” in the ERCOT lower Rio Grande Valley. The NPRR also excludes this new Hub from the existing ERCOT-wide Hub average and Bus average calculations in Sections 3.5.2.6 and 3.5.2.7.
Reason: Market efficiencies or enhancements

Key Documents

Related Content