Summary

Title Implement 95% Facility Rating Limit in the Planning Criteria
Next Group
Next Step
Status Rejected on 08/12/2014

Action

Date Gov Body Action Taken Next steps
08/12/2014 BOARD Rejected
02/11/2014 BOARD Deferred/Tabled ERCOT Board for consideration.
12/03/2013 TAC Recommended for Approval ERCOT Board for consideration.
11/14/2013 ROS Recommended for Approval TAC for consideration.
10/23/2013 PLWG Recommended for Approval ROS for consideration.
09/25/2013 PLWG Recommended for Approval PLWG for Impact Analysis review.
08/28/2013 PLWG Deferred/Tabled PLWG Language Consideration

Voting Record

Date Gov Body Motion Result
08/12/2014 BOARD To reject PGRR031. Passed
02/11/2014 BOARD To table PGRR031. Passed
12/03/2013 TAC To to recommend approval of PGRR031 as recommended by ROS in the 11/14/13 ROS Report. Passed
11/14/2013 ROS To recommend approval of PGRR031 as recommended by PLWG in the 10/23/13 PLWG Report. Passed
10/23/2013 PLWG Consensus to endorse and forward the 9/25/13 PLWG Report as revised by PLWG and the Impact Analysis for PGRR031 to ROS.
09/25/2013 PLWG Consensus to recommend approval of PGRR031 as amended by the 6/27/13 AEP comments and as revised by PLWG.
08/28/2013 PLWG Consensus to table PGRR031

Background

Status: Rejected
Date Posted: Jun 12, 2013
Sponsor: PLWG
Urgent: No
Sections: 4.1.1.2
Description: This Planning Guide Revision Request (PGRR) changes the planning criteria such that system improvements are planned when studies show Facilities will be loaded up to 95% of their applicable rating.
Reason: The Operations and Planning Synchronization Task Force (OPSTF) identified several factors that could lead to overloads in operations that were not observed in planning studies.