PRR702

Summary

Title Emergency Interruptible Load Service
Next Group
Next Step
Status Rejected on 02/22/2007

Action

Date Gov Body Action Taken Next steps
02/22/2007 PRS Rejected

Voting Record

Date Gov Body Motion Result
02/22/2007 PRS To reject PRR702 Passed

Background

Status: Rejected
Date Posted: Dec 19, 2006
Sponsor: Eagle Energy Partners, Enernoc, and Occidental Chemical Corporation
Urgent: Yes
Sections: Section 2, Definitions and Acronyms; Section 4, Scheduling; Section 5, Dispatch; Section 6, Ancillary Services; Section 9, Settlements; Section 12, Market Information System; and Section 16, Registration
Description: Modify the Zonal Protocols to allow for the use of an Emergency Interruptible Load Service (EILS) when an Emergency Electric Curtailment Plan (EECP) is declared and all available Generation and Loads acting as Resources (LaaR) have been deployed.
Reason: On September 15, 2006 ERCOT presented the need for another tool in the EECP toolbox to avoid firm load shed as done on April 17, 2006. This PRR provides ERCOT the requested tool in a manner that is consistent with current market design.