NOGRR195

Summary

Title: Generator Voltage Control Tolerance Band
Next Group:
Next Step:
Status: Approved on 08/11/2020
Effective Date: 02/05/2021

Action

Date Gov Body Action Taken Next Steps
08/11/2020 Board of Directors Approved
07/29/2020 TAC Recommended for Approval Revision Request Consideration
07/09/2020 ROS Recommended for Approval Revision Request Consideration
06/04/2020 ROS Recommended for Approval Impact Analysis Consideration
10/03/2019 ROS Deferred/Tabled Language Consideration
09/05/2019 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
08/11/2020 Board of Directors to approve NOGRR195 as recommended by TAC in the 7/29/20 TAC Report Passed
07/29/2020 TAC to recommend approval of NOGRR195 as recommended by ROS in the 7/9/20 ROS Report Passed
07/09/2020 ROS to endorse and forward to TAC the 6/4/20 ROS Report as amended by the 7/8/20 ERCOT comments and the Impact Analysis for NOGRR195 with a priority of 2020 and rank of 300 Passed
06/04/2020 ROS to recommend approval of NOGRR195 as amended by the 6/2/20 LCRA comments Passed
10/03/2019 ROS to table NOGRR195 and refer the issue to the Voltage Profile Working Group (VPWG) and Operations Working Group (OWG) Passed
09/05/2019 ROS to table NOGRR195 for one month Passed

Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

Background

Status: Approved
Date Posted: 08/20/2019
Sponsor: ERCOT
Urgent: No
Sections: 2.2.10, 2.7.3.1, 2.7.3.3, 2.7.3.4, 2.7.3.5
Description: This Nodal Operating Guide Revision Request (NOGRR) addresses ERCOT audit recommendations from Texas Reliability Entity, Inc. (Texas RE) and proposes to modify generator voltage control tolerance bands.
Reason: Addresses current operational issues

Key Documents