NPRR897

Summary

Title: Adjustments to Black Start Service (BSS) Procurement Timeline and Testing
Next Group:
Next Step:
Status: Approved on 12/11/2018
Effective Date: 12/12/2018

Action

Date Gov Body Action Taken Next Steps
12/11/2018 Board of Directors Approved
11/29/2018 TAC Recommended for Approval Revision Request Consideration
11/15/2018 PRS Recommended for Approval Revision Request Consideration
10/18/2018 PRS Recommended for Approval Impact Analysis Consideration
09/13/2018 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
12/11/2018 Board of Directors to approve NPRR897 as recommended by TAC in the 11/29/18 TAC Report Passed
11/29/2018 TAC to recommend approval of NPRR897 as recommended by PRS in the 11/15/18 PRS Report, with a proposed effective date of upon ERCOT Board approval Passed
11/15/2018 PRS to endorse and forward to TAC the 10/18/18 PRS Report and Impact Analysis for NPRR897 Passed
10/18/2018 PRS to recommend approval of NPRR897 as amended by the 10/15/18 ROS comments as revised by PRS Passed
09/13/2018 PRS to table NPRR897 and refer the issue to ROS Passed

Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

Background

Status: Approved
Date Posted: 08/29/2018
Sponsor: ERCOT
Urgent: No
Sections: 3.14.2, 8.1.1.2.1.5, 22 Attachment M (new)
Description: This Nodal Protocol Revision Request (NPRR) adjusts the timeline for the Black Start Service (BSS) procurement and testing process, adds a weather limitation disclosure form, and aligns the Load-Carrying Test procedure with actual practice.
Reason: Market efficiencies or enhancements

Key Documents