NPRR877

Summary

Title: Use of Actual Interval Data for IDR ESI IDs for Initial Settlement
Next Group:
Next Step:
Status: Approved on 08/07/2018

Action

Date Gov Body Action Taken Next Steps
08/07/2018 Board of Directors Approved
07/26/2018 TAC Recommended for Approval Revision Request Consideration
07/19/2018 PRS Recommended for Approval Revision Request Consideration
06/14/2018 PRS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
08/07/2018 Board of Directors approved NPRR877 as recommended by TAC in the 7/26/18 TAC Report Passed
07/26/2018 TAC to recommend approval of NPRR877 as recommended by PRS in the 7/19/18 PRS Report and as amended by the 7/24/18 ERCOT comments Passed
07/19/2018 PRS to endorse and forward to TAC the 6/14/18 PRS Report and Impact Analysis for NPRR877 with a recommended priority of 2018 and rank of 2290 for Phase 1 and a recommended priority of 2019 and rank of 2540 for Phase 2 Passed
06/14/2018 PRS to recommend approval of NPRR877 as submitted Passed

Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

Background

Status: Approved
Date Posted: 05/17/2018
Sponsor: Oncor
Urgent: No
Sections: 18.6.1
Description: This Nodal Protocol Revision Request (NPRR) provides a process to allow for the use of actual metered interval data for initial settlement of an Operating Day for Electric Service Identifiers (ESI IDs) that currently require BUSIDRRQ Load Profiles. Currently, meter data is sent monthly on the 867_03 for ESI IDs with BUSIDRRQ Load Profiles, so most of the data used for initial settlement for these ESI IDs is estimated using proxy day data. The ESI IDs are resettled with actual data during final Settlement on the 55th day following the Operating Day. The result is inaccurate initial Settlement.
Reason: Market efficiencies or enhancements

Key Documents