MIS LOG IN

NPRR845

Summary

Title RMR Process and Agreement Revisions
Next Group
Next Step
Status Approved on 10/09/2018
Effective Dates
04/05/2019

Action

Date Gov Body Action Taken Next steps
10/09/2018 BOARD Approved
09/26/2018 TAC Recommended for Approval Board for consideration
07/26/2018 TAC Deferred/Tabled TAC for consideration
07/19/2018 PRS Recommended for Approval TAC for consideration
06/14/2018 PRS Recommended for Approval PRS for Impact Analysis review
08/11/2017 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
10/09/2018 BOARD To approve NPRR845 as recommended by TAC in the 9/26/18 TAC Report Passed
09/26/2018 TAC To recommend approval of NPRR845 as recommended by PRS in the 7/19/18 PRS Report as amended by the 9/13/18 ERCOT comments Passed
07/26/2018 TAC To table NPRR845 Passed
07/19/2018 PRS To endorse and forward to TAC the 6/14/18 PRS Report and Impact Analysis for NPRR845 with a recommended priority of 2018 and rank of 2280 Passed
06/14/2018 PRS To recommend approval of NPRR845 as amended by the 6/7/18 WMS comments Passed
08/11/2017 PRS To table NPRR845 and refer the issue to WMS Passed

Background

Status: Approved
Date Posted: Jul 27, 2017
Sponsor: ERCOT
Urgent: No
Sections: 1.3.1.2, 3.14.1.2, 3.14.1.9, 3.14.1.11, 3.14.1.12, 3.14.1.12 (new), 3.14.1.13 (new), 3.14.1.14, 3.14.1.15 (ref), 3.14.1.16, 3.14.1.16 (new), 3.14.1.17, 3.14.1.18, 6.6.6.1, 6.6.6.6, 22B, and 22E
Description: This Nodal Protocol Revision Request (NPRR) incorporates a number of revisions to improve the effectiveness of the Reliability Must-Run (RMR) process.
Reason: Addresses current operational issues. Market efficiencies / enhancements

Key Documents

Related Content