Summary

Title Disallow PTP Obligation Bid Award where Clearing Price exceeds Bid Price by $0.25/MW per hour
Next Group
Next Step
Status Approved on 06/13/2017
Effective Dates
06/29/2017

Action

Date Gov Body Action Taken Next steps
06/13/2017 BOARD Approved
05/25/2017 TAC Recommended for Approval Board for consideration
05/11/2017 PRS Recommended for Approval TAC for consideration
04/13/2017 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
06/13/2017 BOARD To approve NPRR827 as recommended by TAC in the 5/25/17 TAC Report Passed
05/25/2017 TAC To recommend approval of NPRR827 as recommended by PRS in the 5/11/17 PRS Report as revised by TAC with a recommended effective date of upon system implementation Passed
05/11/2017 PRS To recommend approval of NPRR827 as amended by the 5/4/17 WMS comments, as revised by PRS; and to forward to TAC Passed
04/13/2017 PRS To grant NPRR827 Urgent status; to table NPRR827 for one month and refer the issue to WMS Passed

Background

Status: Approved
Date Posted: Apr 11, 2017
Sponsor: Crescent Power, Inc.
Urgent: Yes
Sections: 4.5.1
Description: This Nodal Protocol Revision Request (NPRR) disallows ERCOT from settling PTP Obligations in the DAM where the corresponding clearing price is greater than the bid price for the PTP Obligation by $0.25/MW per hour.
Reason: Addresses current operational issues; prevents unnecessary harm to Market Participants