MIS LOG IN

PGRR046

Summary

Title Addition of Geomagnetically Induced Current (GIC) Model Building Requirements
Next Group
Next Step
Status Approved on 10/11/2016
Effective Dates
09/01/2016

Section 2.2

05/08/2017

Section 6.11

Action

Date Gov Body Action Taken Next steps
10/11/2016 BOARD Approved
07/28/2016 TAC Recommended for Approval Revision Request Consideration
07/07/2016 ROS Recommended for Approval Revision Request Consideration
06/29/2016 PLWG Recommended for Approval Revision Request Consideration
05/18/2016 PLWG Recommended for Approval Impact Analysis Consideration
04/20/2016 PLWG Deferred/Tabled Language Consideration
03/23/2016 PLWG Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
10/11/2016 BOARD To approve PGRR046 as recommended by TAC in the 7/28/16 TAC Report with an ERCOT Board action effective date of 8/9/16. Passed
07/28/2016 TAC To recommend approval of PGRR046 as recommended by ROS in the 7/7/16 ROS Report. Passed
07/07/2016 ROS To recommend approval of PGRR046 as recommended by PLWG in the 6/29/16 PLWG Report. Passed
06/29/2016 PLWG To endorse and forward to ROS the 5/18/16 PLWG Report as revised by PLWG and the Revised Impact Analysis for PGRR046. Passed
05/18/2016 PLWG To recommend approval of PGRR046 as amended by the 4/19/16 Wind Coalition comments as revised by PLWG. Passed
04/20/2016 PLWG To table PGRR046 for one month. Passed
03/23/2016 PLWG To table PGRR046 for one month. Passed

Background

Status: Approved
Date Posted: Feb 26, 2016
Sponsor: ERCOT
Urgent: No
Sections: 2.2, 6.11(new)
Description: This Planning Guide Revision Request (PGRR) aligns the Planning Guides with North American Electric Reliability Corporation (NERC) Reliability Standard TPL-007-1, Transmission System Planned Performance for Geomagnetic Disturbance Events, by specifying a process for developing geomagnetically-induced current system models.
Reason: Regulatory requirements