NPRR878

Summary

Title: ERS Obligation Report for TDSPs
Next Group:
Next Step:
Status: Approved on 12/11/2018
Effective Date: 02/08/2019

Action

Date Gov Body Action Taken Next Steps
12/11/2018 Board of Directors Approved
11/29/2018 TAC Recommended for Approval Board for consideration
07/26/2018 TAC Deferred/Tabled TAC for consideration
07/19/2018 PRS Recommended for Approval TAC for consideration
06/14/2018 PRS Recommended for Approval PRS for Impact Analysis review

Voting Record

Date Gov Body Motion Result
12/11/2018 Board of Directors To approve NPRR878 as recommended by TAC in the 11/29/18 TAC Report Passed
11/29/2018 TAC To recommend approval of NPRR878 as recommended by PRS in the 7/19/18 PRS Report Passed
07/26/2018 TAC To table NPRR878 Passed
07/19/2018 PRS To endorse and forward to TAC the 6/14/18 PRS Report and Impact Analysis for NPRR878 Passed
06/14/2018 PRS To recommend approval of NPRR878 as submitted Passed

Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

Background

Status: Approved
Date Posted: 05/29/2018
Sponsor: CenterPoint Energy
Urgent: No
Sections: 3.14.3.4
Description: This Nodal Protocol Revision Request (NPRR) prescribes ERCOT’s posting of an ERS Obligation Report for Transmission and/or Distribution Service Provider (TDSPs) to the Market Information System (MIS) Certified Area.
Reason: Addresses current operational issues / Regulatory requirements

Key Documents